Re: Material with MRP Type 'P2' planning by APO Heuristics

$
0
0

Hello PK,

 

 

Heuristics will not create a receipt while taking account of the PP/DS planning time fence.

only possible to plan new orders in the planning time fence manually.

 

The planning time fence is valid for both external procurement and in-house production.In the case of external procurement,

Use SAP_PP_002 as product heuristic in APO product master. Maintain PPDS horizon, planning time fence as per requirement.

New planned orders/Preqs created by a heuristic have their availability date on or after the planning time fence.

The "PP-Firmed" indicator is set if one of the firming indicators is set at header level or at a product receipt or if the order is within the planning time fence.

Requirements within the planning time fence can no longer be covered in time by an automatic planning anyway.

In infinite scheduling, reciepts created simultaneously at the end of the planning time fence.

If you want to avoid rescheduling orders within the planning time fence due to a reexplosion, you should use an infinite scheduling strategy during planning.For information on this subject, refer also to note 551124 'APO:Finite scheduling with the MRP heuristic (Documentation)'.

Also note The PP/DS planning time fence is considered during the SNP heuristic run.

 

Best Regards,

R.Brahmankar


Killing user sessions with a job

$
0
0

Hello,

 

We want, in our SCM system, before starting a process chain, to kill all user sessions on all application servers by running a job. Our BW consultants created a job, as a step of their process chain, which kills these sessions. The problem is that user sessions are killed only for the users logged on the server on which the job runs so, as we have 5 application servers, user sessions are killed only for one out of 5 application servers.

 

I suggested to create this job with 5 steps, each step having set as running target server one of the application servers. The BW consultant said this is not possible in the process chain. Could you please suggest a way to run this job in order to kill the user sessions on all application servers?

 

I mention the fact that I am a SAP Basis Admin and have no knowledge on how process chain are working and how can be modified.

 

Br,

Gabriel

Configuration steps for enabling service object in ME21N

$
0
0

Hi Experts,

 

In one of my client there is a requirement of uploading documents ( like .pdf, .doc, .xls etc) in purchase order creation ( ME21N) . Present "Services for Object " option is not available in ME21N.

I have checked configuration steps for this facility in SPRO --> Cross- Application Components --> Document Management --> Control Data --> Maintain Screen for Object Link


Here Sap Object : EKPO and screen no : 248 was already assigned , and in Define Document types option also under KPR type EKPO & Screen no 248 already available.


But still I am not getting that "Services for Object" option  in ME21N.


Please let me know the step by step procedure for activating this option in ME21N.


Thanks in Advance.


Regards,

Aruna.

Re: Killing user sessions with a job

$
0
0

Gabriel,

An individual process chain can be directed to a specific server; this is an attribute of the process chain.  Your unhelpful BW consultants could create 5 small single step process chains, one for each server, and then call them locally within a single process chain; in parallel, or in series.

 

Best Regards,

DB49

Re: Material with MRP Type 'P2' planning by APO Heuristics

$
0
0

Hi Rupesh,

 

We do not want to create new PReq's even after the planning time fence. As i said in my earlier post, we use MRP Type 'P2' in ECC and the MRP was not creating new receipts even after the planning time fence, so basically the new requirements falling wihtin PTF should not be planned even after the PTF.

 

Is there any heuristic to handle such type of planning in APO either by SNP or PPDS.

 

 

Regards

PK

Re: Material with MRP Type 'P2' planning by APO Heuristics

$
0
0

Hello PK,

 

Then you should maintain PPDS horizon = planning time fence. Suppose you have 3 weeks of planning time fence then you should also have PPDS horizon as 3 week. So that Heuristic will plan the receipt within the horizon.


Best Regards,

R.Brahmankar

Analysing Delivery REliabilities in supply chain

$
0
0

a
Hallo FRiends

 

I am in need of your help in the field of SCM. I hope I am in the right group

 

Presently, we have in our company access to Dates like  Available to Promise (WADAT or ETDAT) material level and position level , WADAT-IST (Actual delivery) and Invoice Date but Goods REceipt Date @ Customer is missing . Hence,  I limited my comparision to actual delivery Date EX-Warehouse (WADAT-IST)

 

My actual objective was to find the service Level but I limited myself to Deleivery Reliabilty (How good we are in holding ourselves with Confirmed dates w.r.t Customer Requested Date and at the same time if it is Delivered in Reality (WADAT-IST) as the date confirmed (ATP DATE).

 

I found it how is our Delivery Relibaility in terms of confirming the dates position level  comapring it with actual delivery but I would like to compare it with Purchasing Reliabilty and Production REliabilties too and a use it ias a KPI Key Performance Indicator)

 

To reach to a decision of saying we have delays in delivering goods physically as there was a capacity constraint in production or Purchasing Department or in Shipping Department (The Raw material being late deliverd from supplier OR The finishing Date of Production order was delayed and etc.)

 

 

I want would like to compare it for the 3 departments a comparision weekly or monthly basis to report .

 

Please help me which fields are important to me in purchasing and Production like in SD  we have WADAT-Ist (which is actual Delivery ) and and I have VBEP-WADAT (confirmed Date)

 

In EKET , in purchasing i see SLFDT field and the EINDT but am not sure where to get the fields in purchasing for the actual delivery and at the same time in Production planned Date vs Actual finaishing Date on a material level and on a position level

 

Thanks in advance

 

Waiting for your inputs

 

Beat Regards

 

Could you please try top provide the Inputs

Re: Material with MRP Type 'P2' planning by APO Heuristics

$
0
0

Hi Rupesh,

 

Yes, but i would like to create receipts for the new requirments coming outside of the planning time fence (PTF). Let me explain with an example below:

 

Product Structure: Header product (Currently in ECC MRP Type: P1) and 3 BOM Components (Currently in ECC MRP Type: P2)

 

After CIF'ing all the materials to APO, we have the following dates in APO (giving just as an example)

 

Today's Date: 1st Feb, 2015

 

PP/DS PTF: 10th Feb, 2015 (10 Days)

 

PP/DS Horizon: 10th Feb, 2016 (1 year from PTF)

 

Scenario 1: If there is a new requirement coming on 5th Feb, 2015, i do not want the heuristic to plan/create new receipts (PReq's) even after the PTF. This is how currently it works with MRP Type 'P2' in ECC

 

Scenario 2: If there is a new requirement coming after PTF (for e.g. on 20th Feb, 2015), I want the heuristic to plan for the new receipts based on the requirements date. This is currently working with this above settings, so i do not have to worry about this Scenario 2.

 

 

Please let me know any other idea or work around for the Scenario 1 above. Basically all i want to see the heuristic is to ignore new requirements falling within PTF, but consider new requirements coming in after PTF.

 

Thank you

 

Regards

PK


Re: Material with MRP Type 'P2' planning by APO Heuristics

$
0
0

Hello PK,


If you run SNP planning, SNP planned order will be created out side the PPDS horizon.  SNP planning will cover this demand out side SNP planning horizon.SNP does not create any orders within the SNP production horizon.So in you case the PP/DS horizon should be equal to the SNP production horizon will work for you.

If you run PPDS planning, No new orders will be created  because demand it is out of PPDS planning horizon if inside then you have planning time fence.

Please do read OSS Note 481906 - SNP - PP/DS integration (documentation).

 

Best Regards,

R.Brahmankar

Re: Material with MRP Type 'P2' planning by APO Heuristics

$
0
0

Hi Rupesh,

 

This is not fully solving my problem. I do not want to consider new requirements within PTF, but i do want to consider new requirements outside of the PTF.

 

Also i think changing SNP production horizon value, might impact other planning groups who are using these materials.

 

To limit the scope of planning to only PPDS Heuristic planning, what are the options for the scenario i had mentioned in my earlier message.

 

Regards

PK

Do I need any Certification???

$
0
0

Hi, i finished masters in Logistics and supply chain management from a UK University. I learnt SAP MM during the course work. Well, I havent found any jobs in Uk after graduation.

 

Am currently living in India. Am looking for jobs in India.

 

But, so many questions running in my mind. What sort of jobs do i need to apply for? Do I need any certification in SAP though I did my masters??

Doing SCM job without SAP will give any good career opportunities in future?? Any SAP certifications will help me finding a job?? If so what certification do I need to take up??

 

Plzzzzzzzz help..

 

Thanks

Re: Do I need any Certification???

$
0
0

Hi Swapna,

 

Below is my suggestion-

  • Based on current knowledge and degree try to get job in SCM. In 1st Job experience you will get idea about industry,requirement,business process,operation,how the business runs,logistics  etc.While doing this you can judge your interest whether you are really interested in operation,execution or in systems
  • Try to join the company where SAP MM/SAP SCM module get used.Because of this you can earn hands on experience in SAP which may helpful to you in future.
  • Inventing 3lakh Rs at this stage will not solve your purpose.
  • While doing job learn more & more business process and co-relate with them with SAP system.
  • After 2 or 3 years later  you turn around and think on same question I am sure,You are the only one who can answer better than anyone.
  • With or without certification also you can have great career ahead.Certification will add value after some experience only not at this level.

 

I hope this will help you.Wish you Good luck.

 

Thanks,

Snehal

Re: Do I need any Certification???

$
0
0

thnx a lot

 

I shall do the same....

Storage section check & Master data related issue

$
0
0

Hello All,

 

I have couple of questions regarding the master data set up of WM.

 

1) I have a material with Storage section indicator as 009 and i want to move to a bin which has storage section as 004. This 004 is not maintained in the storage section search. Storage section check active is blank T331-PRBER field is blank. My question is will it allow to put the stocks in 004 storage section as it is not maintained in storage section search?

 

2) In MARM-UMREZ field do we have any limitation of the number? We have few materials currently with  360000 base units per pallet in legacy. Can we keep as it is or should we just keep 99999? In both cases will it have any impact on LHMG1 field?

 

Thanks in advance!

Re: Material with MRP Type 'P2' planning by APO Heuristics

$
0
0

Hi APO Experts,

 

Still i couldn't able to plan the ECC MRP Type 'P2' scenario in SCM APO.

 

Is there any one in the community who has worked with this before and can able to share your thoughts. Thank you.

 

Regards

PK


Re: Material with MRP Type 'P2' planning by APO Heuristics

$
0
0

Hello PK,

 

You can influence the result by using BAdi /SAPAPO/RRP_PLANNING  Change the Planning Results with your custom logic for such planning time fence materials.

BAdI Interface /SAPAPO/IF_EX_RRP_PLANNING

Methods,

  • AFTER_NETTING -With this method, you can change the result of the net requirements calculation or replace the standard net requirements calculation with your own net requirements calculation.

Or

  • RECEIPTS_SAVE -With this method, you can change the list of receipts that the system should schedule, reuse, or reexplode.

 

Best Regards,

R.Brahmankar

Error in phase MAIN_SHDRUN/SUBMOD_FDC_RUN/PARMVNT_FDC - EHP3 upgrade

$
0
0

Hello all,

 

Using SUM while running SCM 7.0 EHP3 upgrade I am getting error in phase MAIN_SHDRUN/SUBMOD_FDC_RUN/PARMVNT_FDC:

 

Checks after phase MAIN_SHDRUN/SUBMOD_FDC_RUN/PARMVNT_FDC were negative!

Last error code set: Single errors (code &gt; 8) found in logfile 'MVNTFDC.ELG'<br/> 1 tp processes returned errors. View latest 'TP*.ECO' files in log-directory for details

 

ERROR: Detected the following errors:

# D:\SUM\abap\log\PD000203.SCD:

3 ETP000 NOT NULL )

3 ETP000 ON [/BIC/FZT_DEL_C1_PSCH000]

3 ETP000 WITH ( DATA_COMPRESSION = PAGE )

3 ETP000

2WETP000 11:10:14: Retcode 1: error in DDL statement for "/1CRR/TG00003781 " - repeat

2EETP345 11:10:26: Retcode 1: SQL-error "2726-Partition function '/BIC/FZT_DEL_C1_PFUN000' uses 1 c

2EETP345 olumns which does not match with the number of partition columns used to partition the tab

2EETP345 le or index." in DDL statement for "/1CRR/TG00003781 "

2 ETP000 --------------- DB-ROLLBACK() ---------------

2EETP334 11:10:26: error in DDL, nametab for "/1CRR/TG00003781" not activated

 

3 ETP000 NOT NULL )

3 ETP000 ON [/BIC/FZT_DEL_C2_PSCH000]

3 ETP000 WITH ( DATA_COMPRESSION = PAGE )

...skipped 18 more lines. Please see MVNTFDC.html for more information.

 

I checked some other log files:

MVNTFDC

 

1 ETQ201 Entering upgrade-phase "MAIN_SHDRUN/SUBMOD_FDC_RUN/PARMVNT_FDC" ("20150203110951")

2 ETQ367 Connect variables are set for standard instance access

4 ETQ399 System-nr = '00', GwService = 'sapgw00' Client = '000'

1 ETQ206 Executing pre-phase DB specific actions.

1 ETQ200 Executing actual phase 'MAIN_SHDRUN/SUBMOD_FDC_RUN/PARMVNT_FDC'.

1 ETQ399 Phase arguments:

2 ETQ399 Arg[0] = 'TP_MOVENTABS_SHD'

2 ETQ399 Arg[1] = 'INTDEL;INTACT;NOBUFFRESET;SHADOW_ONLY'

2 ETQ399 Arg[2] = 'MF=F,STEP=T,RANGE-TS'

2 ETQ399 Arg[3] = 'MVNTFDC.TP0'

1 ETQ399 Using error summary log 'MVNTFDC.ELG'.

1 ETQ399 Using 8 parallel processes

2 ETQ399 Empty putsteps - configuring at least parallel batches and main import processes.

2 ETQ399 Distribute 8 parallel processes to 2 tp and 4 R3trans.

4 ETQ380 computing toolpath for request "TP_MOVENTABS_SHD"

4 ETQ381 request "TP_MOVENTABS_SHD" means "tp mvntabs for shadow tables"

4 ETQ382 translates to group "R3UP_TOOL_GROUP_SHD"

4 ETQ399 Requirement for tp maps to 'exe'

4 ETQ383 translates to path "D:\SUM\abap\exe"

2 ETQ399 Starting 8 tp processes:

4 ETQ010 Starting: tp ddlntabs operation

3 ETQ121 20150203110952: PID 7444 execute 'D:\SUM\abap\exe\tp "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=00" "seltsize=0" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"' in background, output written to 'D:\SUM\abap\log\TP00.ECO'.

2 ETQ399 Started tp ddlntabs with pid 7444

4 ETQ010 Starting: tp ddlntabs operation

3 ETQ121 20150203110952: PID 4888 execute 'D:\SUM\abap\exe\tp "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=01" "seltsize=1" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"' in background, output written to 'D:\SUM\abap\log\TP01.ECO'.

2 ETQ399 Started tp ddlntabs with pid 4888

4 ETQ010 Starting: tp ddlntabs operation

3 ETQ121 20150203110952: PID 9100 execute 'D:\SUM\abap\exe\tp "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=02" "seltsize=2" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"' in background, output written to 'D:\SUM\abap\log\TP02.ECO'.

2 ETQ399 Started tp ddlntabs with pid 9100

4 ETQ010 Starting: tp ddlntabs operation

3 ETQ121 20150203110952: PID 736 execute 'D:\SUM\abap\exe\tp "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=03" "seltsize=3" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"' in background, output written to 'D:\SUM\abap\log\TP03.ECO'.

2 ETQ399 Started tp ddlntabs with pid 736

4 ETQ010 Starting: tp ddlntabs operation

3 ETQ121 20150203110952: PID 8864 execute 'D:\SUM\abap\exe\tp "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=04" "seltsize=4" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"' in background, output written to 'D:\SUM\abap\log\TP04.ECO'.

2 ETQ399 Started tp ddlntabs with pid 8864

4 ETQ010 Starting: tp ddlntabs operation

3 ETQ121 20150203110952: PID 9264 execute 'D:\SUM\abap\exe\tp "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=05" "seltsize=5" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"' in background, output written to 'D:\SUM\abap\log\TP05.ECO'.

2 ETQ399 Started tp ddlntabs with pid 9264

4 ETQ010 Starting: tp ddlntabs operation

3 ETQ121 20150203110952: PID 9732 execute 'D:\SUM\abap\exe\tp "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=06" "seltsize=6" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"' in background, output written to 'D:\SUM\abap\log\TP06.ECO'.

2 ETQ399 Started tp ddlntabs with pid 9732

4 ETQ010 Starting: tp ddlntabs operation

3 ETQ121 20150203110952: PID 11492 execute 'D:\SUM\abap\exe\tp "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=07" "seltsize=7" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"' in background, output written to 'D:\SUM\abap\log\TP07.ECO'.

2 ETQ399 Started tp ddlntabs with pid 11492

3 ETQ123 20150203110954: PID 9264 exited with status 0 (time 0.000 real)

2 ETQ399 tp ddlntabs finished with exit code 0.

3 ETQ123 20150203110954: PID 7444 exited with status 0 (time 0.000 real)

2 ETQ399 tp ddlntabs finished with exit code 0.

3 ETQ123 20150203110954: PID 4888 exited with status 0 (time 0.000 real)

2 ETQ399 tp ddlntabs finished with exit code 0.

3 ETQ123 20150203110954: PID 736 exited with status 0 (time 0.000 real)

2 ETQ399 tp ddlntabs finished with exit code 0.

3 ETQ123 20150203110954: PID 9732 exited with status 0 (time 0.000 real)

2 ETQ399 tp ddlntabs finished with exit code 0.

3 ETQ123 20150203110956: PID 11492 exited with status 0 (time 0.000 real)

2 ETQ399 tp ddlntabs finished with exit code 0.

3 ETQ123 20150203110956: PID 9100 exited with status 0 (time 0.000 real)

2 ETQ399 tp ddlntabs finished with exit code 0.

3 ETQ123 20150203110956: PID 8864 exited with status 0 (time 0.000 real)

2 ETQ399 tp ddlntabs finished with exit code 0.

2 ETQ399 Looking for pattern 'PD00....\.SCD'

2 ETQ399 Wasting log file 'D:\SUM\abap\log\PD000203.SCD'.

1 ETQ124 Scanned file 'log\PD000203.SCD' from offset 9525 to 12695 for errors.

2 ETQ399 Operation 'ddlntabs' looking for pattern 'PD00....\.SCD'

2 ETQ399 Looking for pattern 'PD01....\.SCD'

2 ETQ399 Wasting log file 'D:\SUM\abap\log\PD010203.SCD'.

1 ETQ124 Scanned file 'log\PD010203.SCD' from offset 3394 to 6564 for errors.

2 ETQ399 Operation 'ddlntabs' looking for pattern 'PD01....\.SCD'

2 ETQ399 Looking for pattern 'PD02....\.SCD'

2 ETQ399 Wasting log file 'D:\SUM\abap\log\PD020203.SCD'.

1 ETQ124 Scanned file 'log\PD020203.SCD' from offset 3394 to 6564 for errors.

2 ETQ399 Operation 'ddlntabs' looking for pattern 'PD02....\.SCD'

2 ETQ399 Looking for pattern 'PD03....\.SCD'

2 ETQ399 Wasting log file 'D:\SUM\abap\log\PD030203.SCD'.

1 ETQ124 Scanned file 'log\PD030203.SCD' from offset 3394 to 6564 for errors.

2 ETQ399 Operation 'ddlntabs' looking for pattern 'PD03....\.SCD'

2 ETQ399 Looking for pattern 'PD04....\.SCD'

2 ETQ399 Wasting log file 'D:\SUM\abap\log\PD040203.SCD'.

1 ETQ124 Scanned file 'log\PD040203.SCD' from offset 3394 to 6564 for errors.

2 ETQ399 Operation 'ddlntabs' looking for pattern 'PD04....\.SCD'

2 ETQ399 Looking for pattern 'PD05....\.SCD'

2 ETQ399 Wasting log file 'D:\SUM\abap\log\PD050203.SCD'.

1 ETQ124 Scanned file 'log\PD050203.SCD' from offset 3394 to 6564 for errors.

2 ETQ399 Operation 'ddlntabs' looking for pattern 'PD05....\.SCD'

2 ETQ399 Looking for pattern 'PD06....\.SCD'

2 ETQ399 Wasting log file 'D:\SUM\abap\log\PD060203.SCD'.

1 ETQ124 Scanned file 'log\PD060203.SCD' from offset 3394 to 6564 for errors.

2 ETQ399 Operation 'ddlntabs' looking for pattern 'PD06....\.SCD'

2 ETQ399 Looking for pattern 'PD07....\.SCD'

2 ETQ399 Wasting log file 'D:\SUM\abap\log\PD070203.SCD'.

1 ETQ124 Scanned file 'log\PD070203.SCD' from offset 3394 to 6564 for errors.

2 ETQ399 Operation 'ddlntabs' looking for pattern 'PD07....\.SCD'

2 ETQ399 Starting 1 tp processes:

4 ETQ010 Starting: tp ddlntabs operation

3 ETQ121 20150203111013: PID 8692 execute 'D:\SUM\abap\exe\tp "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=00" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"' in background, output written to 'D:\SUM\abap\log\TP00.ECO'.

2 ETQ399 Started tp ddlntabs with pid 8692

3 ETQ123 20150203111050: PID 8692 exited with status 8 (time 0.000 real)

2EETQ399 tp ddlntabs failed with exit code 8.

2 ETQ399 Operation 'ddlntabs' looking for pattern 'PD00....\.SCD'

1 ETQ124 Scanned file 'log\PD000203.SCD' from offset 12805 to 18826 for errors.

4 ETQ399 html file conversion from 'D:\SUM\abap\log\MVNTFDC.ELG' to 'MVNTFDC.html' succeeded.

4 ETQ010 Date & Time: 20150203111051 

1EETQ399 Last error code set is: Single errors (code > 8) found in logfile 'MVNTFDC.ELG'

1 tp processes returned errors. View latest 'TP*.ECO' files in log-directory for details

1EETQ203 Upgrade phase "PARMVNT_FDC" aborted with errors ("20150203111051")

 

 

TP00.ECO

 

SAPup> Starting subprocess in phase 'TP_ACTION_CP2SINI' at 20150202112054
    ENV: PATHEXT=.COM;.EXE;.BAT;.CMD;.VBS;.VBE;.JS;.JSE;.WSF;.WSH;.MSC
    ENV: PATH=D:\SUM\abap\exe;D:\sapdb\programs\bin;D:\sapdb\programs\pgm;C:\Windows\system32;C:\Windows;C:\Windows\System32\Wbem;C:\Windows\System32\WindowsPowerShell\v1.0\;C:\Program Files (x86)\Windows Imaging\;C:\Program Files\System Center Operations Manager 2007\;D:\Program Files\Microsoft SQL Server\100\Tools\Binn;D:\usr\sap\SCD\SYS\exe\uc\NTAMD64
    ENV: SAPSYSTEMNAME=SCD
    ENV: dbms_type=mss
    ENV: dbs_mss_schema=scd
    PWD: D:\SUM\abap\tmp

EXECUTING D:\SUM\abap\exe\tp.EXE "pf=D:\SUM\abap\var\CP2SHDI.TPP" r3e SAPKBBF740 -s SCD u18
This is D:\SUM\abap\exe\tp.EXE version 380.27.37 (release 741, unicode enabled)
This is D:\SUM\abap\exe\R3trans.exe version 6.24 (release 741 - 11.08.14 - 17:21:00).
unicode enabled version
D:\SUM\abap\exe\R3trans.exe finished (0004).
INFO: No client specified on command line. Taking client 0 from E070C.
tp finished with return code: 4
meaning:
  A tool used by tp produced warnings
SAPup> Process with PID 7592 terminated with status 4 at 20150202112055!
SAPup> Starting subprocess in phase 'PARMVNT_FDC' at 20150202213004
    ENV: PATHEXT=.COM;.EXE;.BAT;.CMD;.VBS;.VBE;.JS;.JSE;.WSF;.WSH;.MSC
    ENV: PATH=D:\SUM\abap\exe;D:\sapdb\programs\bin;D:\sapdb\programs\pgm;C:\Windows\system32;C:\Windows;C:\Windows\System32\Wbem;C:\Windows\System32\WindowsPowerShell\v1.0\;C:\Program Files (x86)\Windows Imaging\;C:\Program Files\System Center Operations Manager 2007\;D:\Program Files\Microsoft SQL Server\100\Tools\Binn;D:\usr\sap\SCD\SYS\exe\uc\NTAMD64
    ENV: SAPSYSTEMNAME=SCD
    ENV: dbms_type=mss
    ENV: dbs_mss_schema=scd
    PWD: D:\SUM\abap\tmp

EXECUTING D:\SUM\abap\exe\tp.EXE "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=00" "seltsize=0" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"
This is D:\SUM\abap\exe\tp.EXE version 380.27.37 (release 741, unicode enabled)
tp finished with return code: 0
meaning:
  Everything OK
SAPup> Starting subprocess in phase 'PARMVNT_FDC' at 20150202213118
    ENV: PATHEXT=.COM;.EXE;.BAT;.CMD;.VBS;.VBE;.JS;.JSE;.WSF;.WSH;.MSC
    ENV: PATH=D:\SUM\abap\exe;D:\sapdb\programs\bin;D:\sapdb\programs\pgm;C:\Windows\system32;C:\Windows;C:\Windows\System32\Wbem;C:\Windows\System32\WindowsPowerShell\v1.0\;C:\Program Files (x86)\Windows Imaging\;C:\Program Files\System Center Operations Manager 2007\;D:\Program Files\Microsoft SQL Server\100\Tools\Binn;D:\usr\sap\SCD\SYS\exe\uc\NTAMD64
    ENV: SAPSYSTEMNAME=SCD
    ENV: dbms_type=mss
    ENV: dbs_mss_schema=scd
    PWD: D:\SUM\abap\tmp

EXECUTING D:\SUM\abap\exe\tp.EXE "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=00" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"
This is D:\SUM\abap\exe\tp.EXE version 380.27.37 (release 741, unicode enabled)
tp finished with return code: 8
meaning:
  A tool used by tp produced errors
SAPup> Process with PID 5336 terminated with status 8 at 20150202213638!
SAPup> Starting subprocess in phase 'PARMVNT_FDC' at 20150203102328
    ENV: PATHEXT=.COM;.EXE;.BAT;.CMD;.VBS;.VBE;.JS;.JSE;.WSF;.WSH;.MSC
    ENV: PATH=D:\SUM\abap\exe;D:\sapdb\programs\bin;D:\sapdb\programs\pgm;C:\Windows\system32;C:\Windows;C:\Windows\System32\Wbem;C:\Windows\System32\WindowsPowerShell\v1.0\;C:\Program Files (x86)\Windows Imaging\;C:\Program Files\System Center Operations Manager 2007\;D:\Program Files\Microsoft SQL Server\100\Tools\Binn;D:\usr\sap\SCD\SYS\exe\uc\NTAMD64
    ENV: SAPSYSTEMNAME=SCD
    ENV: dbms_type=mss
    ENV: dbs_mss_schema=scd
    PWD: D:\SUM\abap\tmp

EXECUTING D:\SUM\abap\exe\tp.EXE "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=00" "seltsize=0" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"
This is D:\SUM\abap\exe\tp.EXE version 380.27.37 (release 741, unicode enabled)
tp finished with return code: 0
meaning:
  Everything OK
SAPup> Starting subprocess in phase 'PARMVNT_FDC' at 20150203102350
    ENV: PATHEXT=.COM;.EXE;.BAT;.CMD;.VBS;.VBE;.JS;.JSE;.WSF;.WSH;.MSC
    ENV: PATH=D:\SUM\abap\exe;D:\sapdb\programs\bin;D:\sapdb\programs\pgm;C:\Windows\system32;C:\Windows;C:\Windows\System32\Wbem;C:\Windows\System32\WindowsPowerShell\v1.0\;C:\Program Files (x86)\Windows Imaging\;C:\Program Files\System Center Operations Manager 2007\;D:\Program Files\Microsoft SQL Server\100\Tools\Binn;D:\usr\sap\SCD\SYS\exe\uc\NTAMD64
    ENV: SAPSYSTEMNAME=SCD
    ENV: dbms_type=mss
    ENV: dbs_mss_schema=scd
    PWD: D:\SUM\abap\tmp

EXECUTING D:\SUM\abap\exe\tp.EXE "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=00" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"
This is D:\SUM\abap\exe\tp.EXE version 380.27.37 (release 741, unicode enabled)
tp finished with return code: 8
meaning:
  A tool used by tp produced errors
SAPup> Process with PID 10396 terminated with status 8 at 20150203102427!
SAPup> Starting subprocess in phase 'PARMVNT_FDC' at 20150203110952
    ENV: PATHEXT=.COM;.EXE;.BAT;.CMD;.VBS;.VBE;.JS;.JSE;.WSF;.WSH;.MSC
    ENV: PATH=D:\SUM\abap\exe;D:\sapdb\programs\bin;D:\sapdb\programs\pgm;C:\Windows\system32;C:\Windows;C:\Windows\System32\Wbem;C:\Windows\System32\WindowsPowerShell\v1.0\;C:\Program Files (x86)\Windows Imaging\;C:\Program Files\System Center Operations Manager 2007\;D:\Program Files\Microsoft SQL Server\100\Tools\Binn;D:\usr\sap\SCD\SYS\exe\uc\NTAMD64
    ENV: SAPSYSTEMNAME=SCD
    ENV: dbms_type=mss
    ENV: dbs_mss_schema=scd
    PWD: D:\SUM\abap\tmp

EXECUTING D:\SUM\abap\exe\tp.EXE "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=00" "seltsize=0" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"
This is D:\SUM\abap\exe\tp.EXE version 380.27.37 (release 741, unicode enabled)
tp finished with return code: 0
meaning:
  Everything OK
SAPup> Starting subprocess in phase 'PARMVNT_FDC' at 20150203111013
    ENV: PATHEXT=.COM;.EXE;.BAT;.CMD;.VBS;.VBE;.JS;.JSE;.WSF;.WSH;.MSC
    ENV: PATH=D:\SUM\abap\exe;D:\sapdb\programs\bin;D:\sapdb\programs\pgm;C:\Windows\system32;C:\Windows;C:\Windows\System32\Wbem;C:\Windows\System32\WindowsPowerShell\v1.0\;C:\Program Files (x86)\Windows Imaging\;C:\Program Files\System Center Operations Manager 2007\;D:\Program Files\Microsoft SQL Server\100\Tools\Binn;D:\usr\sap\SCD\SYS\exe\uc\NTAMD64
    ENV: SAPSYSTEMNAME=SCD
    ENV: dbms_type=mss
    ENV: dbs_mss_schema=scd
    PWD: D:\SUM\abap\tmp

EXECUTING D:\SUM\abap\exe\tp.EXE "pf=D:\SUM\abap\var\MVNTFDC.TPP" ddlntabs SCD "ddlmode=F" "step=T" "protyear=00" shadow_only "strel=701" "substext=4G" "-Dbuffreset=no"
This is D:\SUM\abap\exe\tp.EXE version 380.27.37 (release 741, unicode enabled)
tp finished with return code: 8
meaning:
  A tool used by tp produced errors
SAPup> Process with PID 8692 terminated with status 8 at 20150203111050!

 

 

Can someone please help ?

SAP Auto Id Addon is Not shown in Market place

$
0
0

Hi Gurus,

 

I am not able to see the Addon in Service Mkt Place.

I want to know

Its Required any separate subscription?

Why i cant able to download in my(Company) S user id?

 

What is the procedure to download?

 

Please Guide me on this

 

Thanks and Regards

Anand

MD09 Pegged Requirements in the past

$
0
0

Hi Experts,

 

 

I usually use the Transaction MD09 To know the origin of a necessity, However , after a while this information disappears and can not establish the origin a purchase order or requisition

 

Please could you explain me, when are the pegged requirements broken? (For example with the  goods receipt), and if it is possible to obtain the origin of a necessity or the route from requirement to ERP element for a Purchase order o purchase requisition in the past?

 

Best regards,

 

Alejandro López.

Re: Material with MRP Type 'P2' planning by APO Heuristics

$
0
0

Hi Rupesh,

 

Thanks for your reply again. I am not experienced with BadI, I appreciate if you explain the process step-by-step with the TCodes, that would be much easier to understand. Right now i couldn't able to understand how to work with this BadI so i didn't test the scenario in the system.

 

Regards

PK