Hallo FRiends
I am in need of your help in the field of SCM. I hope I am in the right group
Presently, we have in our company access to Dates like Available to Promise (WADAT or ETDAT) material level and position level , WADAT-IST (Actual delivery) and Invoice Date but Goods REceipt Date @ Customer is missing . Hence, I limited my comparision to actual delivery Date EX-Warehouse (WADAT-IST)
My actual objective was to find the service Level but I limited myself to Deleivery Reliabilty (How good we are in holding ourselves with Confirmed dates w.r.t Customer Requested Date and at the same time if it is Delivered in Reality (WADAT-IST) as the date confirmed (ATP DATE).
I found it how is our Delivery Relibaility in terms of confirming the dates position level comapring it with actual delivery but I would like to compare it with Purchasing Reliabilty and Production REliabilties too and a use it ias a KPI Key Performance Indicator)
To reach to a decision of saying we have delays in delivering goods physically as there was a capycity constraint in production or Purchasing Department or in Shipping Department (The Raw material being late deliverd from supplier OR The finishing Date of Production order was delayed and etc.)
I want to have comapre it for the 3 departments a comparision weekly or monthly basis to report to SCM Team.
Please help me which fields are important to me in purchasing and Production like in SD we have WADAT-Ist (which is actual Delivery ) and and I have VBEP-WADAT (confirmed Date)
In EKET , in purchasing i see SLFDT field and the EINDT but am not sure where to get the fields in purchasing for the actual delivery and at the same time in Production planned Date vs Actual finaishing Date on a material level and on a position level
Thanks in advance
Waiting for your inputs
Beat Regards